Project Overview

EUREKA EFEKTIF was engaged to OEM manufacture piggyback components for a subsea pipeline pigging system under urgent operational requirements. While typical industry lead times are around four months, EUREKA EFEKTIF delivered the components within 11 weeks at a more competitive cost by leveraging its in-house polyurethane engineering and manufacturing capabilities, helping the client maintain its operational schedule.

The Engineering Challenge

Subsea piggyback clamps require high dimensional accuracy and durable materials suitable for subsea operating conditions. In addition, the client required a significantly shorter delivery timeline, as typical overseas suppliers require around four months to complete similar orders.

Engineering Solution

EUREKA EFEKTIF produced the clamps using patented polyurethane material, which has previously been deployed in subsea environments. To ensure precision, a new mould was machined from a solid metal block using CNC, enabling accurate mould dimensions and improved product quality.

Results

The piggyback clamps were successfully delivered within 11 weeks, significantly faster than the typical four-month lead time from other suppliers.

This project demonstrates EUREKA EFEKTIF’s capability to support pipeline operators with fast-track manufacturing of polyurethane subsea pigging components, combining short lead time, cost efficiency, and reliable material performance.

Discuss Your Project with Our Team

If you are planning a pipeline pigging campaign, subsea pipeline modification, or require custom polyurethane engineering components, our team can support your project with design, manufacturing, and fast-track delivery solutions.

Contact EUREKA EFEKTIF today to discuss your project requirements.